How long does it take to tile a bathroom?

Updated

The tiling itself is only part of the job. Most of the time in a bathroom goes on what happens before the first tile and the drying time after it. Here is what's involved, so you can plan around it.

The short answer

For an average family bathroom, the tiling and grouting alone usually takes a few days to a week. A small cloakroom or a single shower wall can be much quicker; a large bathroom with floor-to-ceiling large-format tiles, a wet room or a lot of detail work takes longer. We'll always give you a timeframe for your room before we start.

Stage by stage

  • Stripping out: removing old tiles, and sometimes old plaster or boards behind them.
  • Preparation: repairing, levelling or boarding walls and floors so they're flat and sound. Older houses often need more of this.
  • Waterproofing: tanking shower areas and wet rooms. Many systems need drying time between coats.
  • Setting out: planning where every joint will fall around the bath, window, basin and niches.
  • Tiling: fixing the wall and floor tiles, including all the cuts around pipes, fittings and corners.
  • Setting time: the adhesive needs to set before grouting. Standard adhesive usually needs about a day; rapid-setting adhesive is quicker.
  • Grouting and silicone: filling the joints, cleaning the tiles, and sealing the corners and edges.
  • Curing: grout and silicone need time to cure before the shower is used, usually at least a day. Check the product guidance.

What makes it take longer

  • Uneven or crumbling walls that need levelling or boarding.
  • Large-format tiles, which are slower to handle and need very careful levelling.
  • Lots of small cuts: niches, boxed-in pipes, sloping ceilings and windows.
  • Natural stone, which needs sealing before and after grouting.
  • Wet rooms, where the floor falls and waterproofing add extra stages.
  • Other trades: the plumber and electrician need to do their first fix before tiling and come back afterwards.

How to keep it on track

  • Have your tiles, trims and adhesive delivered before the start date, with a few extra tiles for cuts and breakages.
  • Decide on fittings in advance, so pipe and waste positions are fixed before tiling.
  • Agree the order of work with your plumber and electrician.
  • Plan for the bathroom being out of use, and for a day or two afterwards while everything cures.